7.1 The Standardized Approach

Effective from Dec 28 2022 - Dec 27 2022
To view other versions open the versions tab on the right

The Banks must calculate minimum ORC requirements based on the Standardized Approach by multiplying the BIC and the ILM: 
 
 
ORC = BIC x ILM 
 
 
Where- 
 
 
 (a)Business Indicator Component (BIC) is calculated as the sum of:
 
  (i)12% of the Bank’s BI;
 
 
  (ii)if the Bank’s BI exceeds SAR 4.46 billion, 3% of the amount by which the BI exceeds SAR 4.46 billion; and
 
 
  (iii)if the Bank’s BI exceeds SAR 133.8 billion, 3% of the amount by which the BI exceeds SAR 133.8 billion;2
 
 
BI is elaborated in section 7.2 
 
 
 (b)Internal Loss Multiplier (ILM) is calculated as follow:
 

 
The explanation of ILM is given in section 7.3 
 
 
Risk-weighted assets (RWA) for operational risk are equal to 12.5 times ORC. 
 
 

2 For example, given a BI of SAR 140 billion, BIC = (SAR 140 billion x 12%) + [(SAR 140 billion – SAR 4.46 billion) x 3%] + [(SAR 140 billion – SAR 133.8 billion) x 3%] = (SAR 140 billion x 12%) + (135.54 billion x 3%) + (6.2) x 3%) = SAR 21.05 billion.